ARTICLE · 29 DECEMBER 2016

No reference date, no valid payment claim under NSW Security of Payment Act 1991, says High Court

A "reference date" is a precondition to making a valid payment claim under the SOP Act 1991 (NSW).

AustraliaReal Estate and Construction

Today the High Court of Australia unanimously held that the existence of a "reference date" is a precondition to making a valid payment claim under the Building and Construction Industry Security of Payment Act NSW 1991 (SOP Act). Any purported adjudication determination consequent upon an invalid payment claim would be void and of no effect.

The decision in Southern Han Breakfast Point Pty Ltd (in Liq.) v Lewence Construction Pty Ltd [2016] HCA 52 highlights the importance of including express provisions in contracts dealing with critical issues such as when reference dates will arise, whether reference dates will continue to arise following the termination of the contract, and when rights to payments under the contract may be suspended.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from