New residential strata defect bond and inspection regime coming into effect in NSW

The building bond will be used by the owners corporation to meet the cost of rectifying "defective building work".

AustraliaReal Estate and Construction

On 1 January 2018, Part 11 of the Strata Schemes Management Act 2015 (NSW) and Part 8 of the Strata Schemes Management Regulation 2016 (NSW) will take effect.

The new provisions require a "building bond" (in the form of a bank guarantee or bond) to be provided by the developer of a residential building (or a building for mixed purposes, including residential), for which home warranty insurance is not required, carried out for the purposes of the registration of a strata plan. The building bond must be equal to 2% of the contract price for the building work. Provision of the building bond will be a precondition to obtaining an occupation certificate and must be provided with a copy of the building contract and related documents.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from