Liquidated damages in residential building contracts in New South Wales

A homeowner may now claim for actual damages for delay, in excess of a nominal liquidated damages amount in the contract.

AustraliaReal Estate and Construction

In New South Wales, most contracts for the construction and renovation of residential buildings are largely based off a standard form building contract, such as the HIA Residential Building Contract, that has been specifically drafted for use in relation to residential building work in NSW.

Most residential building contracts will include a clause providing for liquidated damages to become payable to an owner where a builder completes the work after the agreed completion date. The purpose of a liquidated damages clause is to specify a fixed amount of damages payable to the owner if the work is not completed within an agreed timeframe.

Commonly, the standard form building contracts will include a nominal amount for liquidated damages as the default position. However, the NSW Supreme Court has recently determined that such clauses in residential building contracts will not prevent the owners from making a claim for general damages; that is the actual damages suffered

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from