In New South Wales, most contracts for the construction and
renovation of residential buildings are largely based off a
standard form building contract, such as the HIA Residential
Building Contract, that has been specifically drafted for use in
relation to residential building work in NSW.
Most residential building contracts will include a clause
providing for liquidated damages to become payable to an owner
where a builder completes the work after the agreed completion
date. The purpose of a liquidated damages clause is to specify a
fixed amount of damages payable to the owner if the work is not
completed within an agreed timeframe.
Commonly, the standard form building contracts will include a
nominal amount for liquidated damages as the default position.
However, the NSW Supreme Court has recently determined that such
clauses in residential building contracts will not prevent the
owners from making a claim for general damages; that is the actual
damages suffered