Construction contracts, particularly the Australian Standard
general conditions, routinely include liquidated damages clauses
requiring one party to pay damages arising from some breach of
contract or a defect. Such terms will be unenforceable as a penalty
clause if the amount does not represent a genuine pre-estimate of
the loss the non breaching party will incur as a result of the
breach.
The Supreme Court of Queensland was recently asked to consider a
modified AS4300-1995 general conditions contract and determine
whether or not the liquidated damages clause was a penalty clause.
The Court in Grocon Constructors (Qld) Pty Ltd v Juniper
Developer No. 2 Pty Ltd, held the liquidated damages clause
was enforceable and its reasoning is helpful for all parties
negotiating and drafting liquidated damages clauses in construction
contracts.