Current Position
As Development Consents are expensive and time consuming to
obtain, their retention has always been critical to developers,
mining companies and landowners.
Normally a Development Consent will lapse a date 5 years after
the date it is granted, unless there is physical
commencement of "building, engineering or
construction work relating to the building, subdivision or
work" which takes place on the site before the expiry date of
the consent.
To stop a Development Consent from lapsing requires certain
actions to be undertaken by way of works or activities on the site.
See section 4.53 of the Environment Planning and Assessment Act
1979 (NSW) (the Act) which sets out the statutory
requirements, namely;