Lapsing development consents in NSW – Change of activities to consider

As development consents are expensive to obtain, retention is critical to developers, mining companies and landowners.

AustraliaReal Estate and Construction

Current Position

As Development Consents are expensive and time consuming to obtain, their retention has always been critical to developers, mining companies and landowners.

Normally a Development Consent will lapse a date 5 years after the date it is granted, unless there is physical commencement of "building, engineering or construction work relating to the building, subdivision or work" which takes place on the site before the expiry date of the consent.

To stop a Development Consent from lapsing requires certain actions to be undertaken by way of works or activities on the site. See section 4.53 of the Environment Planning and Assessment Act 1979 (NSW) (the Act) which sets out the statutory requirements, namely;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from