ARTICLE · 23 MAY 2013

Landmark Queensland Court of Appeal decision confirms developers’ protection against the wrongful refusal to settle by purchasers - 22 May 2013

This case is the first of its kind and clarifies the meaning of Section 27, giving assurance and comfort to developers.

AustraliaReal Estate and Construction

HopgoodGanim has successfully acted for the Receivers and Managers of Queensland's Port of Airlie Boathouse development in defending an attempt by a purchaser of a proposed lot to avoid their contract pursuant to Section 27(2) of the Land Sales Act 1984 (Act).

Section 27(2) gives a purchaser the right to avoid a contract for the sale of a proposed lot if the vendor has not given a registrable instrument of transfer within 3½ years after the date of the contract.

The landmark Queensland Court of Appeal decision of Meridien AB Pty Ltd & Anor v Jackson & Ors was handed down yesterday and unanimously upheld Meridien's appeal with costs. The Court of Appeal held that the proper construction of Section 27(2) did not permit a purchaser to avoid their contract in circumstances where they refused to settle and the 3½ year sunset period subsequently expired. This case is the first of its kind and clarifies the meaning of Section 27, giving some assurance and comfort to