Introduction
On Thursday 18 July 2019, the New South Wales Land and
Environment Court published its decision in the long running case
involving the former Alexandria Landfill Site at St Peters. This
land was acquired by Roads and Maritime Services
(RMS) for the St Peters Interchange for Stage 3 of
the WestConnex Project.
The case involved a claim of $583 million by companies in the
Dial A Dump Group then controlled by Mr Ian Malouf. This claim is
possibly the largest claim for compensation following the
acquisition of land in NSW history.
Dr Nick Brunton and Anneliese Korber, partners of Norton Rose
Fulbright, acted for RMS in the proceedings and also acted for RMS
in a large number of other cases involving surrounding land.