The judment was an application where the MCG, an original unsuccessful submitter, sought leave to be joined as a party.

AustraliaReal Estate and Construction

Robertson DCJ

Download the judgment

Practice and procedure – where developer seeks to change condition of preliminary development approval by this Court – where original unsuccessful submitter appellant seeks to be joined as a party – where developer opposes leave – where Council and DERM support leave being given – whether the presence of the submitter would be desirable and just to enable the court to effectively adjudicate

Facts: This was an application in pending proceeding brought by Mackay Conservation Group Inc (MCG) for an order pursuant to r. 69(1)(b) of the Uniform Civil Procedure Rules 1999 that it be included as a party to an application by Eastpoint Mackay Pty Ltd (Eastpoint) to amend a condition of a preliminary development approval, which condition was imposed as part of a suite of conditions imposed by the Court after a lengthy unsuccessful appeal by MCG as an adverse submitter against Council's decision to approve the development.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from