IN BRIEF - PRACTICAL COMPLETION CANNOT BE BACKDATED ON A
CERTIFICATION OF PRACTICAL COMPLETION.
Practical completion (PC) occurs on the date a certificate of PC
is issued by the Superintendent, even if the certificate states
that PC occurred on an earlier date, the contractor claims that PC
was achieved earlier, and the Superintendent agrees that PC was
achieved earlier. This was the (perhaps surprising) conclusion of
the Court of Appeal in Abergeldie
Contractors Pty Ltd v Fairfield City Council [2017] NSWCA
113.
The case concerned Australian Standard contract terms that are
relevantly similar to those used on most construction projects in
Australia. The date of PC is a contractual trigger point that has
consequences for liquidated damages entitlements, extension of time
and delay damages claims, early completion bonuses, defects
liability periods, final payment claims, warranties, security, care
of the works, insurance and payment claims under the
Building and