Fair value claims are sometimes available, even when there is no right to be paid under a construction contract.

AustraliaReal Estate and Construction

Claims for the fair value (quantum meruit) of a construction contractor's works are sometimes available when there is no right to be paid under a construction contract.

Where the contractual payment regime fails part-way through the works, the contractor's fair value claim is not always equal to the percentage of works completed times the total contract price.

Objectors say this violates the sanctity of the bargain between principal and contractor by substituting the courts' valuation of the contractors' works for the value that the parties themselves agreed to give to the works by their own contract.

However, properly understood, it is precisely out of a concern not to interfere with the bargain between contractor and principal that courts will not apportion the contract price for work that is incomplete.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.