Share on LinkedInShare on LinkedIn

ARTICLE · 19 FEBRUARY 2018

HHG Construction Law Series Part 19: No challenge to adjudication award within power: High Court

An adjudicator's determination cannot be challenged in a court unless the adjudicator had no power to make that award.

AustraliaReal Estate and Construction

On 14 February 2018, the High Court of Australia unanimously decided that an adjudicator's determination of a construction pay dispute cannot be challenged in a court unless the adjudicator had no power to make that determination. To say that the determination was based on a misinterpretation of the law or of the relevant construction contract is simply not enough.

This was the long-awaited finding of the High Court in two related cases that were heard and decided at the same time: Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4 and Maxcon Constructions Pty Ltd v Vadasz [2018] HCA 5. Having been handed down by the highest court in Australia, this is the final word on the question whether an adjudicator's mistaken interpretation of the law or a contract is enough for a State Supreme Court to review and quash that adjudicator's payment award. The High Court's answer to that question in each case was a resounding no.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from