Significant increases in maximum penalties for
development offences and changes to how costs are awarded in the
Planning and Environment Court have now come into
effect.
This article is the last in our series examining the key
provisions of the Planning Act 2016. In this edition, we will also
consider the new Planning and Environment Court Act 2016. Both Acts
are expected to commence on 3 July 2017.
Development offences
The Planning Act introduces a significant increase in the
penalty for committing a development offence, with the maximum
penalty for an offence committed by an individual being increased
to 4,500 penalty units ($548,550.00) from 1,665 penalty units
($202,963.50). A maximum penalty of 17,000 penalty units
($2,072,300.00) applies where a development offence relates to
undertaking assessable development on a Queensland Heritage place
or a Local Heritage Place without a development permit. Note that
the maximum penalty that applies to a corporation