Share on LinkedInShare on LinkedIn

ARTICLE · 22 SEPTEMBER 2014

Extended limitation period for breach of contract claims for defective building work in Victoria

Contractors and consultants in construction work should review all insurance arrangements to ensure sufficient coverage.

AustraliaReal Estate and Construction

Key Points:

Victorian owners now have 10 years from the issue of the occupancy permit in which to bring a claim in contract or tort for defective building work. Contractors and consultants undertaking construction work (or design in relation to that work) should now review their insurance arrangements to ensure their coverage is sufficient.

In cases of defective building work, the usual position has been that claims in contract and tort must be brought within six years of the cause of action arising.

The recent Victorian Court of Appeal decision of Brirek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd [2014] VSCA 165 has upset that understanding, holding that section 134 of the Building Act 1993 (Vic) means that an owner has 10 years from the issue of the occupancy permit in which to bring a claim in contract or tort for defective building work