Epc Contracts In The Renewable Energy Sector - South African Re Ipp Programme - Lessons Learned From Phases 1 And 2 (October 2012) Part 9

Further information on EPC contracts.

AustraliaReal Estate and Construction

No breach

3.7 The Owner will not be in breach of any obligation under this Contract by reason only of the Contractor being denied permission to export power to the Transmission System and/or Distribution System in accordance with the Codes for reasons attributable directly or indirectly to the Contractor and/or the performance of the Facility as a whole.

No deemed Commercial Operation

3.8 The Contractor acknowledges that there will not be any deemed Commercial Operation as a result of the connection of the Facility to the Transmission System or the sale of any electricity.

Code requirements

3.9 The Contractor must perform the Works (including the Connection Works) to ensure that the Owner and Contractor [its Personnel and Subcontractors] each comply with the requirements of any Responsible Authorities and each Party's obligations under the: