Epc Contracts In The Renewable Energy Sector - South African Re Ipp Programme - Lessons Learned From Phases 1 And 2 (October 2012) Part 8

A discussion of performance testing in EPC contracts.

AustraliaReal Estate and Construction

Post COD Performance Tests

1.19 The Contractor must give the Owner prior written notice of when it intends to carry any of the Post COD Performance Tests at the times and in accordance with the requirements set out in Schedule 8 (Tests).

1.20 As soon as reasonably practicable after receipt of a notice under clause 1.19, the Owner must issue a notice to the Contractor specifying the date for commencement of the Post COD Performance Tests at the times and in accordance with Schedule 8 (Tests).

Final Completion

1.21 The Contractor must notify the Owner at least 10 Days before whole of the Works and Facility will, in the opinion of the Contractor, reach the stage of Final Completion.