Epc Contracts In The Renewable Energy Sector - South African Re Ipp Programme - Lessons Learned From Phases 1 And 2 (October 2012) Part 10

More information on EPC contracts.

AustraliaReal Estate and Construction

EP is the relevant Evaluation Period stated elsewhere in this Contract;

i is the sequential number of each Measurement Period in the Evaluation Period;

MP is the relevant Measurement Period of [15 minutes] each;

is the unshaded insolation (kWh/m²) in the plane of array measured in accordance with paragraph 2.7 below during the relevant Measurement Period.

2 MEASURED PRMP

2.1 Determination of Measured PRMP

Measured PRMP shall be determined and calculated as follows:

whereby:

Measured PRMP is the Measured PR (dimensionless) for the relevant Measurement Period;

MP is the relevant Measurement Period;

EbACis the energy actually metered (kWh) by the HV meter at Delivery Point during the Measurement Period; [Drafting note: If energy generated by the Facility is used to provide auxiliary power (rather than drawing auxiliary power from the grid), it would be appropriate to add the auxiliary power to EAC. However, in such case there should be