The NSW Parliament has recently passed amendments to the
Environmental Planning and Assessment Act 1979 (NSW)
(Act) and Environmental Planning and
Assessment Regulation 2021 (NSW)
(Regulation), which mandate longer exhibition
periods for development applications made by councils or which
involve land owned or occupied by councils.
Council-related developments
With effect from 3 April 2023, council-related
development applications must remain on public exhibition for a
minimum of 28 days, compared to the regular 14-day period for most
other development applications.
A new definition of "council-related development
application" will be inserted into the Act, meaning a
development application, for which a council is the consent
authority, that is: