Assisted by Elisabeth Krstanovski
The case of Mistrina Pty Ltd v Australian Consulting
Engineers Pty Ltd [2020] NSWCA 223 highlights that third-party
professionals in building disputes can found be liable for causing
loss if their conduct was a material cause of the loss. In this
case, the Court held a design engineer liable for loss suffered by
a property developer by relying on an erroneous certification of a
structurally defective raft slab, although the design engineer was
not directly contracted by the developer.
Background
In 2009, Mistrina Pty Ltd (Developer) entered
into a contract with Jabbcorp Management Pty Ltd
(Builder) for the construction of a 10-storey
development in Brighton-Le-Sands (Development)
funded by a loan facility from Bankwest (Bank).
The Developer, Builder and Bank entered into a tripartite deed,
which allowed the Bank the right to assume the Developer's
obligation under the building contract following 'Event of
Default'.