Even if the construction contract is declared unenforceable, that may not completely disentitle a contractor to payment.

AustraliaReal Estate and Construction

In Nichols v Earth Spirit Homes Pty Ltd [2015] QCA 219 (Nichols), the Queensland Court of Appeal held that a contract for 'building work'1 which did not comply with section 67G of the QBCC Act was, nonetheless, enforceable.

Rider

Generally we do not start these e-alerts with a disclaimer, but, on this occasion, it is necessary to make it clear that we are not suggesting that oral contracts for 'domestic building work'2 are enforceable. That is clearly not the case3.

Facts

In 2007, Mr Nichols entered into a contract with Earth Spirit Homes Pty Ltd (Earth Spirit) for the construction of 10 houses. However, the parties terminated that contract in 2012. Subsequently, Mr Nichols and Earth Spirit entered into an oral agreement. It was a term of that agreement that Mr Nichols would pay Earth Spirit a weekly 'management fee' to complete the project. A dispute arose as to the payment of the management fee. At first instance (before the Queensland Civil