Development approval for building work thwarted by failure to obtain consent from parties benefitting from easements on the land

Application of the strict operation of s65 Building Act 1975.

AustraliaReal Estate and Construction

IN BRIEF

The case of ISPT Pty Ltd v Brisbane City Council & Anor [2017] QPEC 52 concerned a submitter appeal in the Planning and Environment Court commenced by ISPT Pty Ltd against a preliminary approval for the partial demolition of the Embassy Hotel in Brisbane's City Centre.

The Court found in favour of the Appellant but held that, had it not been for the strict operation of section 65 of the Building Act 1975, the appeal would have otherwise been dismissed. The following issues were considered by the Court:

  • whether the development proposal conflicted with the Heritage overlay code;
  • whether there was a conflict with the relevant performance outcomes of the Brisbane City Plan 2014; and