Developers in NSW take heed - Sunset clauses are no longer an excuse to wiggle out of contracts

The new law seeks to protect buyers by placing certain requirements on developers in respect of rescinding the contract.

AustraliaReal Estate and Construction

Jobema Developments Pty Limited v Zhu & Ors

The addition of section 66ZL of the Conveyancing Act dealing with sunset dates ("New Sunset Clause Law") has attracted a lot of attention, particularly in light of the recent decision of Jobema Developments Pty Limited v Zhu & Ors [2016] NSWSC 3.

A sunset clause within a Contract of Sale specifically addresses the final date ("sunset date") a developer has to complete the project. The inclusion of this clause protects developers who may experience common delays such as problematic weather and financial availability. If the developer has failed to complete the project by the Sunset date, each party is given the opportunity to rescind the contract within 14 days.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from