Facts

In this UK case, a firm of architects nominated a project leader who then did not lead the project in question. The owner sought to refurbish a private members' club in London and entered into discussions with the architects, Fitzroy Robinson. The architects represented both orally and in bid documents that Mr Blake, who was a director of the company, would be the team leader for the project.

Mr Blake tendered his resignation to the company in March 2006, at about the time when Fitzroy Robinson was to commence works and before contracts had been finalised. Mr Blake's contract of employment required him to stay on for a further 12 months after tendering his resignation.