The recent New South Wales Court of Appeal decision of Parkview Constructions Pty Ltd v The Owners - Strata Plan No 90018 has provided clarification on the application of limitation periods when homeowners or bodies corporate seek to amend existing claims when new defects arise.

The background to the appeal

The case before the Court was a claim by The Owners - Strata Plan No 90018 (the body corporate) for a large building with 286 residential apartments, and parking and storage spaces on the outskirts of the Sydney-CBD. The body corporate brought the claim against Parkview Constructions (the builder) and The Quay Haymarket (the developer).

The building was registered as a strata plan on 1 September 2014. A final occupation certificate was issued on 15 December 2014.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from