In brief - Damages correspond to cost of making work conform to
specifications
The Supreme Court of NSW has found that a capping layer and a
layer of fill which were placed on a development site in NSW
departed substantially from specification because the project
manager failed to take reasonable steps to ensure that a consultant
supervised the works.
Assessment of damages for breaches of quality obligations in
engineering projects
In the case
Bannister & Hunter v Transition Resort Holdings (No.2)
[2013] NSWSC 1943, the Supreme Court of NSW recently confirmed
the principles to be adopted in assessing damages for breaches of
quality obligations in engineering projects.
In doing so, it dealt with the troubling and recurring issues of
reasonableness in the method and cost of rectification and whether
damages should be reduced or negated by a subsequent sale of the
property affected. The court also considered the meaning of
"reasonable steps" to be taken by a