Damages awarded for breach of contractual obligations of project management and contract supervision in NSW

The NSW court confirmed the principles in assessing damages for breaches of quality obligations in engineering projects.

AustraliaReal Estate and Construction
Faith Laube
Faith Laube

In brief - Damages correspond to cost of making work conform to specifications

The Supreme Court of NSW has found that a capping layer and a layer of fill which were placed on a development site in NSW departed substantially from specification because the project manager failed to take reasonable steps to ensure that a consultant supervised the works.

Assessment of damages for breaches of quality obligations in engineering projects

In the case Bannister & Hunter v Transition Resort Holdings (No.2) [2013] NSWSC 1943, the Supreme Court of NSW recently confirmed the principles to be adopted in assessing damages for breaches of quality obligations in engineering projects.

In doing so, it dealt with the troubling and recurring issues of reasonableness in the method and cost of rectification and whether damages should be reduced or negated by a subsequent sale of the property affected. The court also considered the meaning of "reasonable steps" to be taken by a