Court Of Appeal Decision For Off The Plan Sales In Queensland

The Queensland Court of Appeal has delivered its much anticipated judgement in the case of Bossichix Pty Ltd v Martinek Holdings Pty Ltd [2009] QCA 154; a case that is of importance for all off the plan sales of lots in community titles schemes in Queensland.

AustraliaReal Estate and Construction

The Queensland Court of Appeal has delivered its much anticipated judgement in the case of Bossichix Pty Ltd v Martinek Holdings Pty Ltd [2009] QCA 154; a case that is of importance for all off the plan sales of lots in community titles schemes in Queensland.

The Court of Appeal has held that s 212 Body Corporate and Community Management Act 1997 (BCCMA) requires contracts to provide for the settlement to be a minimum period of 14 days after notice to the buyer that the community titles scheme for the lot sold has been established and that a reference to plan registration alone will not be sufficient to satisfy the BCCMA requirements.

Commonly, off the plan contracts provide for settlement to occur a specified period after completion of construction and title to the lot sold. In Queensland, the BCCMA requires that the contract states that settlement must not take place earlier than 14 days after the scheme has been established. Establishment of a community titles