Introduction
In the recent case of St. Hilliers Construction Pty Ltd (In
Administration) v. Fitzpatrick Investments Pty Ltd [2012]
NSWSC 804, the New South Wales Supreme Court held that the
contractor was not entitled to have its security reduced at
practical completion because it had not complied with the relevant
contractual pre-conditions. The case serves as an important
reminder to contractors to carefully consider the requirements
under their contracts for the return of security (usually retention
monies or a third party bond/guarantee) and to ensure that these
requirements are properly satisfied.
The case concerns a D&C contract for the construction of a
commercial building in Docklands, Melbourne. The contract obliged
the contractor to provide three bank guarantees amounting to 5 per
cent of the contract sum. The works achieved practical completion
on 31 October 2011, coinciding with the date that the principal
took physical possession of the works. Shortly