Court insists on compliance with contractual pre-conditions for the release of security

This case is a reminder to contractors to carefully consider the contractual requirements for the release of security.

AustraliaReal Estate and Construction

Introduction

In the recent case of St. Hilliers Construction Pty Ltd (In Administration) v. Fitzpatrick Investments Pty Ltd [2012] NSWSC 804, the New South Wales Supreme Court held that the contractor was not entitled to have its security reduced at practical completion because it had not complied with the relevant contractual pre-conditions. The case serves as an important reminder to contractors to carefully consider the requirements under their contracts for the return of security (usually retention monies or a third party bond/guarantee) and to ensure that these requirements are properly satisfied.

The case concerns a D&C contract for the construction of a commercial building in Docklands, Melbourne. The contract obliged the contractor to provide three bank guarantees amounting to 5 per cent of the contract sum. The works achieved practical completion on 31 October 2011, coinciding with the date that the principal took physical possession of the works. Shortly

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from