Court awards damages for building works not completed in a reasonable time

The Court determined an implied term of the contract required that building works be completed within a reasonable time.

AustraliaReal Estate and Construction

Renovations dragging on? A recent decision determined there was an implied term that building works be completed within a reasonable period of time.

In brief

In a recent Supreme Court case1, the Court overturned a VCAT judgment and held as follows:

  1. There was an implied term requiring building works to be completed within a reasonable period of time.
  2. Damages were awarded by reference to the rental value of the property during the delayed period.

Facts

  The Court outlined the facts as follows:

  • Yun Zeng (Zeng) purchased a whole floor apartment at Eureka Tower in Melbourne for $5,838,000.00. The apartment was a shell and required fit out works before it could be occupied.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances. Madgwicks is a member of Meritas, one of the world's largest law firm alliances.

See more popular content from