A Protracted History
In April 2025, Justice Musikanth of the WA Supreme Court
delivered his judgment in Henderson v Contaminated Sites
Committee [2025] WASC 123 (Henderson).
The decision was the latest development in a 15-plus year
process that is yet to finally determine responsibility for the
contamination of a parcel of land used as a service station.
The land in question was classified in 2007 as "possibly
contaminated – investigation required".
In 2016 the WA Contaminated Sites Committee (CSC) determined
responsibility to remediate the contamination of the land (First
Determination of Responsibility).
The First Determination of Responsibility was appealed to the WA
Supreme Court.