Case Note: Patel v Southern Cross Joinery Pty Limited [2022] NSWCATCD 162

The NSW Civil and Administrative Tribunal (NCAT), unlike any other Court, can make costs orders and work orders. Contractors must behave professionally when carrying out construction works.

AustraliaReal Estate and Construction

The NSW Civil and Administrative Tribunal (NCAT), unlike any other Court, can make costs orders and work orders. Contractors must behave professionally when carrying out construction works. Otherwise, Contractors may have costs ordered against them, rather than a work order to fix the defective works.

Principals should also be aware that NCAT will exercise its discretion when deciding whether to adopt expert recommendations on whether to apply a margin on top of costs orders for itemised defective works.

This article looks at a recent decision in which both these principles were applied.

Background

In Patel v Southern Cross Joinery Pty Limited  [2022] NSWCATCD 162, Nandini Patel (Patel) contracted with Southern Cross Joinery Pty Limited (Southern Cross) for the supply and installation of cabinetry. Patel claimed that Southern Cross' building work was not reasonably fit for a specified purpose and in breach of statutory warranties under the Home Building

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from