Case Law Update - The Court´s Reluctance To Stay Enforcement Warrants Obtained Through Adjudication

The Court held that this risk alone is not a sufficient ground to order a stay of the warrant, without other factors coming into play (such as deliberate delay on the part of the builder).

AustraliaReal Estate and Construction

Adam Carlton-Smith
Michelle Hall
Peter Lamont
Rebecca Roylance
Andre Dauwalder

RJ Neller Building P/L v Ainsworth [2008] QCA 397 (9 December 2008)

Facts

The Applicant (Ainsworth) was the owner of a residential property at Noosa Heads. Ainsworth entered into a Queensland Master Builders Association Minor Works Contract with the Respondent (Neller) to carry out renovations to the property. Ainsworth claimed that the works were defective and refused to make all payments claimed by Neller.

Neller submitted a payment claim for $59,907.09 under the Building and Construction Industry Payments Act 2004. This was disputed by Ainsworth and the matter proceeded to adjudication. On 28 March 2007, it was adjudicated that Ainsworth was obliged to pay Neller the sum of $50,771.74.