We all know how expensive building works can become. In some
industries, it is not unheard of for projects to be priced in
excess of $10bn. Obviously, the contractor whose job it is to get
the labour and materials on site and coordinate the complex
workflows would not survive too long financially if they did not
get paid during the course of the works. This is why construction
contracts invariably provide for progress payments, either because
the contract expressly provides for it, or because it is an implied
term under the Construction Contracts Act.
It is important to remember that progress payments are interim
payments on account only. Where the contract is a lump sum or fixed
price contract that sets out a scope of works and a price to be
paid to the contractor for completing it, the principal does not
become indebted to the contractor for any part of the contract
price until the works are substantially completed. Substantial
completion means completion of the