Share on LinkedInShare on LinkedIn

ARTICLE · 27 JUNE 2012

BCIPA: Court of Appeal Declares Pre-conditions for Reference Dates in Contract Void

A clause in a construction contract creating preconditions was declared void because it contracted out of the BCIPA.

AustraliaReal Estate and Construction

Summary

This update considers an important Queensland Court of Appeal decision, delivered on 8 June 2012, regarding the Building and Construction Industry Payments Act 2004 (Qld) (BCIPA).1

The court held that a clause in a contract, which had the effect of prohibiting the service of a payment claim until certain conditions had been met – in other words creating preconditions – was void because it contracted out of the BCIPA.

Some of the preconditions in this case were that the payment claim:

  1. be in the format required by the respondent, including the provision of a statutory declaration
  2. must contain evidence reasonably required by the respondent.

Whether a provision is void under s 99 of the BCIPA is a question of degree. For example in a 2010 Queensland Supreme Court decision2, a contract requiring the submission of a draft claim and a progress certificate by a superintendent before a payment claim could be served was not contracting out of