On 2 November 2016, Justice Stevenson of the Supreme Court of New South Wales delivered a favourable decision for builders in NSW in Owners Corporation Strata Plan 76841 (the Owners Corporation) v Ceerose Pty Ltd & Anor [2016] NSWSC 1545.

One of the key takeaway points from the decision is that the Court would not grant leave to the Owners Corporation to introduce new claims because the 10 year long stop period pursuant to section 109ZK of the Environmental Planning and Assessment Act 1979 (EPA Act) had expired. This is because Ceerose, the contractor, had lost an opportunity to prosecute viable and realistic cross-claims therefore suffering obvious and significant prejudice if leave was allowed to introduce any new claims.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from