SOP claims are restricted if contracts do not state that reference dates survive termination or do not define the work.

AustraliaReal Estate and Construction

In brief – SOP claims will be more restricted where contracts do not state that reference dates survive termination or do not define the work to include preparatory/subsequent activities.

Assuming it is not overturned on appeal, a recent NSW Supreme Court case may change the way you make claims, defend adjudications and draft your construction contracts.

Contract terminated for convenience before completion

In the case Patrick Stevedores Operations No. 2 Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [2014] NSWSC 1413, Patrick Stevedores engaged McConnell Dowell to upgrade its Port Botany Container Terminal, but terminated for convenience before completion. McConnell Dowell made a $55 million claim under the Building and Construction Industry Security of Payment Act 1999 (Act). It relied upon clause 39A.2 of the contract which entitled it to claim for work performed and plant/materials ordered before termination, for demobilisation costs and for a