Share on LinkedInShare on LinkedIn

ARTICLE · 22 JULY 2010

Agreements to Refer Disputes to Mediation or Expert Determination: Anything more than bare bones required?

This article explores the validity of contractual clauses that purport to refer disputes to expert determination or mediation without providing specific rules or procedures for the operation of such a process

AustraliaReal Estate and Construction

1144 Nepean Highway Pty Ltd v. Leigh Mardon Australasia Pty Ltd [2009] VSC 317

It is not unusual to see in construction contracts a short-form clause referring particular disputes to mediation or expert determination without the particular rules or procedures for the mediation or expert determination being specified. If both parties remain happy to go to mediation or expert determination they will ordinarily do what is necessary (including signing documents required by the mediator or expert) to give effect to his or her engagement. However, if one party has had a change of mind since the contract was first entered into that party might not be so co-operative.

In the Supreme Court case, 1144 Nepean Highway Pty Ltd v. Leigh Mardon Australasia Pty Ltd [2009] VSC 317, one of the parties refused to sign the terms of engagement required by the nominated expert. In that case, the clause in the contract provided for disputes to be resolved by an expert to be appointed for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from