After a delay of 141 weeks a builder is entitled to payment after an owners contract termination

Builder is able to recover full payment despite extreme delay in completing works.

AustraliaReal Estate and Construction

Can a builder still recover payments due under a building contract after being 141 weeks late in completing works?

Key takeaways

  • Despite the owner terminating a building contract for serious delay and breach by the builder in failing to provide supporting documents for progress claims, a recent Supreme Court decision found that the builder was entitled to recover full payment
  • The builder delayed completing works for 141 weeks and ran $1 million over-budget but was still able to recover the contract price
  • Unless the contract otherwise provides, a builder who completes the works, where the unpaid cost of the works has been assessed, may claim the balance of the contract price notwithstanding the builder fails to provide supporting documents for progress claims as required by the contract

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from