Adjudicator favours Claimant’s Submission over Respondent’s: Not bad faith, just bad luck

A discussion on the recent case, Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd & Ors. This case reinforces the Court’s view on progress payment applications for adjudication under the Building and Construction Industry Payments Act 2004 (BCIPA).

AustraliaReal Estate and Construction

Peter Lamont, Senior Associate

A recent case, Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd & Ors, reinforces the Court's view that progress payment applications for adjudication under the Building and Construction Industry Payments Act 2004 (BCIPA) are a fast track interim measure to resolving disputed progress claims, but allow for further civil proceedings should the parties pursue their contractual rights. This can create a problem if an adjudicator awards a progress payment to a claimant, and then the claimant goes into liquidation, leaving the respondent with little ability to claw back the progress payment.

The Court gives adjudicators sufficient discretion in their decision making process and recognises that as adjudicators are specialists in their field, they are entitled to come to their own conclusions based on the materials provided. It's also important to keep in mind that adjudicators deal with complex matters within tight

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from