Defence claims not constrained by dispute resolution clauses in Australian Standard AS2124-1992

The dispute resolution clause in AS2124-1992 General Conditions doesn't bar defendants from raising a counterclaim.

AustraliaLitigation, Mediation & Arbitration

Key Points:

The dispute resolution clause of the Australian Standard AS2124-1992 General Conditions doesn't bar defendants from raising a counterclaim.

For anyone involved in construction contracts, the dispute resolution clause of the Australian Standard AS2124-1992 General Conditions has raised some questions. Does it survive termination? Does a claim have to have gone through the process under the dispute resolution clause before it can be raised by way of defence in proceedings?

A recent decision by Justice Kenneth Martin in Jamac Construction Group Pty Ltd v De Mol Investments Pty Ltd [2014] WASC 273 examined the scope of clause 47 of AS2124-1992, which sets out the parties' obligations for dispute resolution. Significantly, the Court held that a defendant who has not instigated the dispute resolution provision under the contract in respect of a claim is not prevented from raising that claim in its defence or by way of counterclaim.