Can you enforce your dispute resolution clause in a standard construction contract?

The court held that the dispute resolution clause in many standard construction contracts is uncertain and unenforceable.

AustraliaLitigation, Mediation & Arbitration

The Victorian Supreme Court decision of WTE Co-Generation & Anor V RCR Energy Pty Ltd & Anor held that the dispute resolution clause in many standard construction contracts is uncertain and unenforceable.

Background

WTE Co-Generation (WTE) contracted with RCR Energy Pty Ltd (RCR) for the supply of a co-generation facility. WTE claimed RCR had breached the contract, issued a notice to terminate and commenced proceedings in relation to the dispute.

The issue

The contract contained a dispute resolution clause that stated:

"Within 7 days after receiving a notice of dispute, the parties shall confer at least in the presence of the Superintendent. In the event the parties have not resolved the dispute then within a further 7 days a senior executive representing each of the parties must meet to attempt to resolve the dispute or to agree on methods of doing so. At every such conference each party shall be represented by a person having authority to agree to such