In brief - Building companies should consider a risk assessment
of past projects
While an effectuated DOCA extinguishes all claims that existed
at the time when a company was placed into administration, the law
is not yet settled on whether this is also the case for latent
defects claims which were not known at the time. To mitigate risk,
building companies considering a DOCA should review all past
projects.
DOCAs extinguish all known claims when company is placed into
administration
In the building industry, it is common for defects to remain
unknown for an extended period of time. During the intervening
period the building company may have appointed an administrator,
proceeded to a DOCA and effectuated the DOCA. One of the outcomes
of an effectuated DOCA is that all claims that existed at the time
when the company was placed into administration are extinguished.
The question is whether a claim relating to a latent defect, which
was not known to exist at the