A statutory demand issued between 25 March 2020 and 31 December 2020 must provide a demand period of six months.

AustraliaInsolvency/Bankruptcy/Re-Structuring

This week's TGIF considers the decision of Re GT's Cooking Oils Pty Ltd [2021] NSWSC 93 in which the court refused a winding up application based on a statutory demand which failed to provide the extended demand period of six months as required under the Coronavirus Economic Response Package Omnibus Act 2020 (Cth).

Key takeaways

  • A court may refuse to make a winding up order if the application is based on a statutory demand which was issued between 25 March 2020 and 31 December 2020 and which fails to provide the requisite demand period of six months.

  • If a statutory demand issued during that period did not allow the debtor six months to satisfy the demand, then waiting for more than six months from the date of issue of the statutory demand to commence winding up proceedings will not cure the defect.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.