What can enable a WA local government to withhold, or not issue, a building permit?

There are circumstances in which a local government can refuse or indeed must refuse to grant a building permit in WA.

AustraliaGovernment, Public Sector

Section 20 of the Building Act 2011 appears to give the local government no discretion at all. Under Section 20(1) of the Act, a local government must grant a building permit if it is satisfied of no fewer than 19 different matters. On the other hand, under Section 20(2) it must not grant the application unless it is satisfied as to each of those matters.

Of course, the granting of a building permit can be deferred if further information is sought under Section 18. That is to be required within a specified time of not more than 21 days. If the time limit passes and the information has not been provided, the local government may refuse to consider the application, although it is not obliged to do so.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from