Tram Delays, Negligent Driver Pays

Metrolink Victoria Pty Ltd (Yarra Trams) was recently successful in the Victorian Court of Appeal in a matter that will shape the future application of the test of reasonable foreseeability and redefine the range of losses recoverable from tortfeasors.

AustraliaGovernment, Public Sector

Metrolink Victoria Pty Ltd (Yarra Trams) was recently successful in the Victorian Court of Appeal in a matter that will shape the future application of the test of reasonable foreseeability and redefine the range of losses recoverable from tortfeasors. In the case of Metrolink Victoria Pty Ltd v Inglis [2009] VSCA 227, Yarra Trams successfully argued that losses sustained under a contractual incentive regime were recoverable from a third party who had negligently caused delays to the tram network.

Yarra Trams operates its services pursuant to a franchise agreement with the State Government. The agreement contains an incentive scheme by which Yarra Trams is financially rewarded for its close adherence to a master timetable and is penalised for deviations from it. Any delay occasioned to the tram network results in a loss to Yarra Trams under the incentive regime, either by way of a reduction in the payment it receives or an increase in the penalty it pays under the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from