Share on LinkedInShare on LinkedIn

ARTICLE · 21 JUNE 2012

Queensland's first compensation case under the Land Access Regime - What does (and doesn't) it mean?

This case provides the first judicial guidance on the land access regime, but doesn't resolve all of the uncertainty.

AustraliaEnergy and Natural Resources

Key Points:

The Peabody case provides the first judicial guidance on the land access regime, but doesn't resolve all of the uncertainty.

The Land Court has recently handed down its first decision on compensation under the new land access regime (Peabody West Burton Pty Ltd v Mason [2012] QLC 0023). This case concerned the proposed undertaking of advanced activities, being four drill pads, 3km of main tracks and 3km of minor tracks, on an exploration permit for coal under the Mineral Resources Act 1989 (Qld) (MRA). The total drill program was expected to be of 12 days duration.

This case provides the first judicial guidance on the land access regime. However, the case does not resolve all of the uncertainty in the way the legislation operates and will be applied. This article will examine what the case means and, perhaps more importantly, what the case does not mean for future land access negotiations and agreements.