Out of control: Is a delay by a subcontractor or supplier a delay beyond your control?

The case highlights the importance of proper drafting of contractual clauses if they are relied upon at a later time.

AustraliaCorporate/Commercial Law

Yara Nipro Pty Ltd v Interfert Australia Pty Ltd [2010] QCA 128

Companies in every industry may face delays caused by weather, suppliers, subcontractors and other unforeseeable delays. Contracts often consider the occurrence of such delays by providing a 'force majeure clause' for instances where delay is considered to be beyond the reasonable control of either party. A recent Queensland Supreme Court decision has highlighted that in such circumstances the drafting of a clause will play a crucial role in assessing whether a 'force majeure clause' will operate to limit liability for delays caused by events seemingly outside either party's control.

In brief

  • Interfert Australia Pty Ltd ('Interfert') agreed to supply Yara Nipro Pty Ltd ('Yara') with goods. Interfert then subcontracted with another supplier, who agreed to supply Interfert with the required goods

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from