News and developments
No excuses for substandard work
Introduction
In a recent judgment delivered on the 6 June 2025, the First Hall Civil Court (the “FHCC”), in the case Raymond Azzopardi (the “Claimant”) vs Adrian Borg (the “Respondent”) presided by Madame Justice Audrey Demicoli, considered the legal obligations of contractors concerning the standard of skill and craftsmanship required under a contract of works.
The Claimant requested the FHCC to (i) declare and decide that the Respondent shall pay the Claimant and is consequently a debtor of the Claimant in connection with any sum due for works carried out at the Respondent’s property, (ii) liquidate the sum which shall be due to the Claimant in the amount of €37,286.74 with the appointment of experts engaged by this Honourable Court should their assistance be necessary, (iii) order the Respondent to pay the Claimant the amount liquidated with costs including those of the judicial letter and precautionary garnishee order filed against the Respondent.
The Background
The dispute emerged following construction works carried out by the Claimant at a site in Luqa owned by the Respondent. The works included those that were covered by the necessary Planning Authority permits, specifically at ground floor level, while additional works needed at first floor level were arranged through verbal agreements and lacked the necessary permits. Despite various payments being made throughout the relationship, the Respondent withheld a significant outstanding sum.
The Respondent contended that the Claimant proceeded with the works independently, disregarding instructions from the appointed architect Mark Frendo, and alleged that the quality of workmanship was substandard and posed considerable risks. These concerns ultimately led to an intervention by the Building and Construction Authority (“BCA”) which ordered termination of works in May 2023.
The Respondent, in his Sworn Reply, held that:
Key issues before the Court
The FHCC proceeded to address the following key issues:
Technical Expert & Quantity Surveyor’s report
At the Claimant’s request, the FHCC appointed Architect Michael Lanfranco and Quantity Surveyor Kevin Borg to assess the works. Following a site visit, the report concluded as follows:
Nonetheless, the Court made reference to Article 618 of Chapter 12 which provides that the court is in no way bound to accept those conclusions made in a technical expert’s report.
Works which were allegedly not carried out in accordance with the level of skill and craftsmanship
The Court examined the Claimant’s admissions, where he conceded that parts of the works were executed without oversight from the architect and absences of the necessary permits for the works to be carried out at ground floor level. As to other works, the Claimant held that the architect was not involved at this stage. The Court also asked whether he was given proper plans, and the Claimant stated that he was only given a piece of paper by the Respondent. In fact, Architect Mark Frendo agreed with this and held that there were works which were not carried out under his supervision and which were not covered by the required permits. It also transpired that the Claimant used to follow instructions given by the Respondent who is an Engineer.
While the Claimant did not contest the fact that certain works were not carried out with the required level of craftsmanship, he nonetheless tried exonerating himself from responsibility claiming that the works were carried out on the instructions of the Respondent. However, the FHCC firmly rejected this defence, affirming that contractors remain fully responsible for ensuring the quality and legality of their work, regardless of client instructions that contravene professional standards or legal requirements. A contractor is bound to carry out works with a certain level of skill and craftsmanship.
The Court further emphasised that the contractor bears the responsibility to perform works to a professional standard, and that delegation of responsibility to the client is not a valid excuse for subpar or unlawful execution of works.
The FHCC additionally held that reports made with the BCA, irrespective of who actually made these reports (the Claimant or Architect Mark Frendo), further substantiate that the works carried out were not of the level of trade and craftsmanship expected.
Determination of Amount Payable
First and foremost, the Court held that it certainly cannot grant payment for works which were not executed to the requisite standard once it resulted that:
Naturally, given that it was the Respondent himself who engaged and authorised the Claimant to perform certain works, all remedial works that are necessary are to be carried out by the Respondent at his own expense.
The FHCC took into consideration the following:
After taking the above into account, the FHCC determined that the Respondent owed the Claimant the sum of €4,266 together with interest from the date of judgment to the date of effective payment.
Decision
In conclusion and for the above-mentioned reasons, the FHCC ruled in favour of the Claimant, declaring Adrian Borg liable to pay Raymond Azzopardi the sum of €4,266 for construction works carried out at BVA Engineering, Plot 143, Industrial Estate Luqa, and dismissed all the Respondent’s pleas in their entirety.
Disclaimer: Ganado Advocates is responsible for contributing to this law report but was not in any way involved as legal advisor for the parties in the judgement being covered in this law report. This article was first published in ‘The Malta Independent’ on 25/06/2025.