Federal Circuit Affirms That The Government Not Liable For Contractor's Costs Of Dealing With Outbreak

Peckar & Abramson, P.C.
Peckar & Abramson, P.C.
Contributor
Peckar & Abramson, P.C.

Peckar & Abramson, P.C.

As a firm dedicated to the needs of its clients in the construction industry, P&A employs over 100...

View firm profile
Explore more from Peckar & Abramson, P.C.

In an earlier blog, we wrote about the Civilian Board of Contract Appeals' (CBCA) decision denying a contractor's claim for the costs of demobilizing from a construction site due to concerns...

United StatesGovernment, Public Sector

In an earlier blog, we wrote about the Civilian Board of Contract Appeals' (CBCA) decision denying a contractor's claim for the costs of demobilizing from a construction site due to concerns about performing work during an Ebola virus outbreak in Appeal of Pernix Serka Joint Venture v. Department of State, CBCA No. 5683 (April 22, 2020). The Pernix case was of interest to many government contractors because it was an indication of how the Government was likely to respond to contractor claims for additional costs due to COVID-19.

In Pernix, the contractor sought to recover its additional costs resulting for a shutdown and remobilization due to an Ebola outbreak. The contracting officer had provided the contractor with a time extension but denied the contractor's cost claim stating that there was no contractual basis for a price adjustment. The contractor appealed the contracting officer's final decision to the CBCA who ultimately granted the Government's motion for