On September 14, 2026, the Armed Services Board of Contract Appeals (“ASBCA”) denied the Government’s motion to dismiss the delay portion of an appeal by Hensel Phelps Construction Company (“Hensel Phelps”), finding that Hensel Phelps did indeed include a sum certain in its Claim. See Hensel Phelps Construction Company, ASBCA No. 64327, 2026 WL 3049122 (Sept. 14, 2026).
The Claim and the Government’s Challenge
Hensel Phelps sought $22,050,672 for delay-related general conditions and other direct costs arising from construction of the Bureau of Engraving and Printing’s Western Currency Facility Expansion Project in Fort Worth, Texas. Its certified claim requested 285 days of compensable delay and included a detailed narrative, a critical-path-method window analysis, exhibits, financial appendices, and subcontractor pass-through claims.