On October 23, 2025, Department of Energy ("DOE") Secretary Chris Wright sent a letter to the Federal Energy Regulatory Commission ("FERC" or "Commission") directing it to initiate a rulemaking...

United StatesEnergy and Natural Resources

On October 23, 2025, Department of Energy ("DOE") Secretary Chris Wright sent a letter to the Federal Energy Regulatory Commission ("FERC" or "Commission") directing it to initiate a rulemaking to accelerate the interconnection of large loads (>20 megawatts) to the transmission system. The letter cites the urgent need to support AI data center and manufacturing demand, requiring "extraordinary quantities of electricity and substantial investment in the Nation's interstate transmission system."

Along with the letter, DOE included an Advance Notice of Proposed Rulemaking ("ANOPR") directing FERC to initiate rulemaking procedures under seldom-used authority in section 403 of the Department of Energy Organization Act. The ANOPR outlines legal justifications for FERC's authority over large-load interconnections and articulates 14 principles to guide the Commission's rulemaking. Secretary Wright requested that FERC take "final action" on the rulemaking by April

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from