MNRE Clarifies That No NOC Is Required Where ESS Is Charged Using Non-RE Power And Sold Through Merchant/third-party Sale Mode.

Sagus Legal
Sagus Legal
Contributor
Sagus Legal

Sagus Legal

We are a full-service law firm providing comprehensive legal advisory and advocacy to clients. Our...

View firm profile
Explore more from Sagus Legal

The Ministry of New and Renewable Energy (“MNRE”) vide office memorandum dated 11.04.2026, has issued a clarification stating that No-Objection Certificate (“NOC”) is not required in certain cases under the Firm and Dispatchable Renewable Energy (“FDRE”) Standard Bidding Guidelines (“FDRE Bidding Guidelines”).

IndiaEnergy and Natural Resources

MNRE clarifies that no NOC is required where ESS is charged using non-RE power and sold through merchant/third-party sale mode.

The Ministry of New and Renewable Energy (“MNRE”) vide office memorandum dated 11.04.20261, has issued a clarification stating that No-Objection Certificate (“NOC”) is not required in certain cases under the Firm and Dispatchable Renewable Energy (“FDRE”) Standard Bidding Guidelines (“FDRE Bidding Guidelines”).

MNRE, upon examining the relevant provisions of the FDRE Bidding Guidelines noted as follows:

  1. Energy Storage System (“ESS”) is a storage component and not a Renewable Energy (“RE”) generating source.
  2. Power discharged from ESS does not qualify as RE power where such ESS is charged using non-RE sources and is therefore ineligible for supply under the FDRE Power Purchase Agreement (“PPA”) framework as renewable power.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from